




The project
A three-story timber-frame building was constructed on the existing school grounds. With construction costs of around CHF 2.7 million, an energy-efficient school building was created that meets high ecological standards. A full-surface in-roof photovoltaic system enables the use of renewable energy. The attic remains unfinished as a reserve for future expansion. Modern, bright classrooms ensure a good learning environment. They are complemented by spacious group rooms, and the cloakroom area can also be used for group work. The classrooms, built to meet today's requirements, create optimal learning conditions and strengthen the educational location of the central community.
The construction method
The building was designed entirely in timber construction from the floor slab upwards. The stairwell with integrated elevator shaft was constructed using an encapsulated solid wood construction method. The roof was designed as a classic pitched roof. The exterior walls and parts of the interior walls were constructed using a timber frame construction method. The ceilings consist of hollow box elements with acoustically effective wood paneling. The uninsulated attic remains as a reserve for future expansion.
The challenge
The tight budget called for simple, streamlined, and economical component structures that still met the requirements for sound and room acoustics. The few wall panels used for bracing absorb high forces and transfer them to the floor slab via inserts.
Construction Data
- Glued laminated timber 92 m3
- Cross-laminated timber CLT 35 m3
- Hollow box ceiling 620 m2
Construction costs
- BKP 1-9: CHF 2.8 million
- BKP 2: CHF 2.7 million
- BKP 214: CHF 880'000
Services of Timbatec
- SIA Phase 31 Preliminary design
- SIA Phase 32 Construction project
- SIA Phase 41 Tendering and comparison of bids
- SIA Phase 51 Implementation project
- SIA Phase 52 Execution
- Specialist planning: building physics
- Structural engineering and construction
- Wood structural engineering
- Support in specialist planning building physics
Architect
Freiluft Architekten BSA SWB SIA
3150 Schwarzenburg
Client
Gemeinde Riggisberg
3132 Riggisberg
Timber construction
Remund Holzbau AG
3150 Schwarzenburg
Photography
david aebi fotograf
3008 Bern